NEC3 Engineering and Construction Contract Flow Charts

Online Shop | Books for your Business | Construction Books etc | NEC Contracts, Manuals and Books | NEC3 Contracts and Guidance Notes |  NEC3 Engineering and Construction Contract Flow Charts

NEC3: Engineering and Construction Contract Flow Charts

Free UK delivery on NEC3: Engineering and Construction Contract Flow Charts

In Paperback Format
NEC3: Engineering and Construction Contract Flow Charts

£22.50
 RRP: £25.00
You save £2.50 (10.0%)
ISBN
9780727759054
Published by
Thomas Telford Ltd
Publication Date
1 April 2013
Format
Paperback
Extent
138 pages
Dimensions
A4 (210 x 297 mm)

To enable users to understand the operation of the Engineering and Construction Contract, this book contains flow charts which set out the procedural logic of the 75 clauses that can be presented with benefit by flow charting.

Construction Clients' Board endorsement of NEC3
The Construction Clients' Board (formerly Public Sector Clients' Forum) recommends that public sector organisations use the NEC3 contracts when procuring construction.

Standardising use of this comprehensive suite of contracts should help to deliver efficiencies across the public sector and promote behaviours in line with the principles of Achieving Excellence in Construction.

OGC endorsement of NEC3
OGC advises public sector procurers that the form of contract used has to be selected according to the objectives of the project, aiming to satisfy the Achieving Excellence in Construction (AEC) principles. This edition of the NEC (NEC3) complies fully with the AEC principles. OGC recommends the use of NEC3 by public sector construction procurers on their construction projects

This publication replaces the previous edition (ISBN: 9780727733672) 
Flow charts
  • 13 Communications
  • 14 The Project Manager and the Supervisor
  • 15 Adding to the Working Areas
  • 16 Early warning
  • 17 Ambiguities and inconsistencies
  • 18 Illegal and impossible requirements
  • 19 Prevention
  • 20 Providing the Works
  • 21 The Contractors design
  • 22 Using the Contractors design
  • 23 Design of Equipment
  • 24 People
  • 25 Working with the Employer and Others
  • 26 Subcontracting
  • 27 Other (Contractor) responsibilities
  • 30 Starting, Completion and Key Dates
  • 31 The programme
  • 32 Revising the programme
  • 33 Access to and use of the Site
  • 34 Instruction to stop or not to start work
  • 35 Take over
  • 36 Acceleration
  • 40 Tests and inspections
  • 41 Testing and inspection before delivery
  • 42 Searching for and notifying Defects
  • 43 Correcting Defects
  • 44 Accepting Defects
  • 45 Uncorrected Defects
  • 50 Assessing the amount due S
  • 51 Payment
  • 52 Defined Cost
  • 53 The Contractors share (Option C and D)
  • 54 The Activity Schedule (Option A and C)
  • 55 The Bill of Quantities (Option B and D)
  • 60 Compensation events
  • 61 Notifying compensation events
  • 62 Quotations for compensation events
  • 63 Assessing compensation events
  • 64 The Project Managers assessments
  • 65 Implementing compensation events
  • 70 The Employers title to Plant and Materials
  • 71 Marking Equipment, Plant and Materials outside the Working Areas
  • 72 Removing Equipment
  • 73 Objects and materials within the Site
  • 80 Employers risks
  • 81 Contractors risk
  • 82 Repairs
  • 83 Indemnity
  • 84 Insurance cover
  • 85 Insurance policies
  • 86 If the Contractor does not insure
  • 87 Insurance by the Employer
  • 90 Termination
  • 91 Reasons for termination
  • 92 Procedures on termination
  • 93 Payment on termination
  • W1 Dispute resolution (used unless Option Y(UK)2 applies)
  • W2 Dispute resolution (used when Option Y(UK)2 applies)
  • X1 Price adjustment for inflation (used only with Options A, B, C and D)
  • X2 Changes in the law
  • X3 Multiple currencies (used only with Options A and B)
  • X4 Parent company guarantee
  • X5 Sectional Completion
  • X6 Bonus for early Completion
  • X7 Delay damages
  • X12 Partnering
  • X13 Performance bond
  • X14 Advanced payment to the Contractor
  • X15 Limitation of the Contractors liability for his design to reasonable skill and care
  • X16 Retention (not used with Option F)
  • X17 Low performance damages
  • X18 Limitation of liability
  • X20 Key Performance Indicators (not used with Option X12)
  • Y(UK)2 The Housing Grants, Construction and Regeneration Act 1996
  • Y(UK)3 The Contracts (Rights of Third Parties) Act 1999


Online Shop | Books for your Business | Construction Books etc | NEC Contracts, Manuals and Books | NEC3 Contracts and Guidance Notes |  NEC3 Engineering and Construction Contract Flow Charts

Civil Service Yearbook
The new Civil Service Yearbook 53rd Edition - Pre-order now.
Civil Service Yearbook 52nd Edition available now
Buy The Civil Service Yearbook
IMDG Code
2014 Edition
The new IMDG Code is in stock now.
IMDG Code 2014 available now
Buy The IMDG code
New Products

The Report of the Iraq Inquiry

Police Workforce, England and Wales, 30 September 2016

European Pharmacopoeia 9th Edition Book Subscription 2017 (9.0, 9.1 and 9.2)

Fire Statistics: Great Britain, 2014-2015

Non-domestic rating: Business Floorspace 2016

The Annual Abstract of Statistics for Benefits, and Indices of Prices and Earnings 2016 Edition

Annual Bus Statistics Light Rail and Tram Statistics Blue Badge Scheme Statistics 2015/16

Bookmark us via QR code
Worldwide Delivery
Secure Payment
Secure Payment
Best Sellers

Dorema U-tabs for ADR/RID 2017

UN ADR 2017 (Books) Two Volume Set

IMDG Code 2016 Edition (inc Amdt 38-16) Book (2 vols)

HSE Approved Codes of Practice - Six Pack (6 Pack) Pack of 6 Books

IATA Dangerous Goods Regulations (DGR) 58th Edition 2017 (Regular Bound)

IMDG Code 2014 Edition (inc Amdt 37-14) Book (2 vols)